Practice interviews

Why did profit rise when revenue fell?

Put a dollar value on each driver and reconcile the total.

The question

You support an invented maintenance business. All figures are in USD. Each job is completed and billed in the same month.

Monthly operating figures
PlanLatest
Jobs1000900
Charge per job ($)100110
Variable cost per job ($)6065
Fixed cost ($)2000020000

Fictional monthly inputs. Rates apply to each completed job.

Case assumptions

Use a volume-first bridge. Change the charge next, then variable cost per job, then fixed cost.

“Why did profit rise when revenue fell?”

A strong answer, step by step

Open each step in turn. This is one strong answer, not the only one.

Step 1: Isolate volume

What would you do here? Open the move you’d make.

  • Isolate volume

    The strong move. 100 fewer jobs at $40 planned contribution reduces profit by $4,000.

  • Use $100 planned revenue per job for profit

    Tempting, but it misses something. That skips the $60 variable cost saved per lost job.

See how a strong candidate says it

“100 fewer jobs at $40 planned contribution reduces profit by $4,000.”

What a strong candidate could say

Why it works: That skips the $60 variable cost saved per lost job.

Step 2: Isolate charge

What would you do here? Open the move you’d make.

  • Apply the $10 increase to 1,000 jobs

    Tempting, but it misses something. The bridge has already moved volume to 900.

  • Isolate charge

    The strong move. The $10 charge increase on 900 jobs adds $9,000.

See how a strong candidate says it

“The $10 charge increase on 900 jobs adds $9,000.”

What a strong candidate could say

Why it works: The bridge has already moved volume to 900.

Step 3: Isolate unit cost

What would you do here? Open the move you’d make.

  • Isolate unit cost

    The strong move. The $5 cost increase on 900 jobs subtracts $4,500.

  • Leave unit cost out because total costs fell

    Tempting, but it misses something. The unit cost rose. Fewer jobs explain the fall in total costs.

See how a strong candidate says it

“The $5 cost increase on 900 jobs subtracts $4,500.”

What a strong candidate could say

Why it works: The unit cost rose. Fewer jobs explain the fall in total costs.

Step 4: Reconcile profit

What would you do here? Open the move you’d make.

  • Report only that profit beat plan

    Tempting, but it misses something. The total conceals the volume miss and higher unit cost.

  • Reconcile profit

    The strong move. Fixed cost is unchanged. Net change is +$500, from $20,000 to $20,500. Revenue fell $1,000.

See how a strong candidate says it

“Fixed cost is unchanged. Net change is +$500, from $20,000 to $20,500. Revenue fell $1,000.”

What a strong candidate could say

Why it works: The total conceals the volume miss and higher unit cost.

The answer, in short

Decision
Fixed cost is unchanged. Net change is +$500, from $20,000 to $20,500. Revenue fell $1,000.
Because
The $5 cost increase on 900 jobs subtracts $4,500.
What would change it
A change in the order of the bridge moves the interaction between drivers.

Common traps

  • Use $100 planned revenue per job for profit
  • Apply the $10 increase to 1,000 jobs
  • Leave unit cost out because total costs fell
  • Report only that profit beat plan

Check your answer

  • Isolate volume
  • Isolate charge
  • Isolate unit cost
  • Reconcile profit